Change Order Log

A tracking document listing every change order on a project, whether pending, approved, or rejected, its value, and its cumulative effect on the contract's overall price and schedule.

Why it matters

A single change order is easy to track in isolation, but a project's cumulative change order total, visible only in a maintained log, is what actually reveals whether a project's scope has drifted significantly from what was originally bid, a trend an owner or GC needs to see building before it becomes a budget surprise at closeout.

On a real project

A project manager reviewing the change order log notices the cumulative approved change order total has quietly reached nearly ten percent of the original contract value. Flagging that trend to the owner well before closeout, rather than it surfacing as a surprise in the final accounting, gives both sides time to manage the budget impact proactively.

Who this matters most to

The Contracts Administrator maintains the change order log and its running totals, and the Project Manager reviews cumulative change order trends against the contingency budget throughout the project.

Where this goes wrong

A project tracks each change order individually as it's approved, without a maintained log showing the cumulative running total, and doesn't realize how significantly the original contract value has grown until the final accounting at closeout reveals it all at once.