Field Order / Architect's Supplemental Instruction (ASI)

A formal written direction from the design team clarifying or slightly adjusting the work, issued when the change is minor enough that it doesn't affect contract price or time, distinct from a construction change directive, which is used specifically when cost or schedule impact is expected.

Why it matters

Treating every minor clarification as if it needs the heavier process of a full change order would bog down a project in paperwork; an ASI or field order exists specifically so small adjustments can be directed quickly, though a contractor who believes a supposedly minor instruction actually does affect cost or time still has to raise that promptly rather than silently absorb it.

On a real project

The architect issues an ASI slightly repositioning a wall-mounted fixture a few inches to clear an unforeseen duct run, a minor field adjustment with no cost or schedule impact. The contractor implements it the same day, without it needing to go through a full change order process.

Who this matters most to

The Project Engineer logs and tracks every ASI issued on a project, and the Contracts Administrator watches for an ASI that, despite being labeled minor, may actually carry a cost or time impact worth raising before simply complying with it.

Where this goes wrong

A contractor receives an ASI that actually does add real cost or time to the work, but implements it without raising the issue, assuming the ASI label itself means no compensation is available, and loses the chance to recover costs it may have been entitled to if it had flagged the impact before proceeding.