Inspection and Test Plan (ITP)

A document, prepared before work begins on a specific scope item, listing every inspection and test required for that work, who performs each one, what standard it's checked against, and which checks require sign-off before the work can proceed to the next step.

Why it matters

Without an ITP spelling out exactly which checks are required and in what order, a crew can cover up work, like backfilling a trench, before a required inspection actually happens, and uncovering already-completed work to inspect it after the fact is far more disruptive and costly than inspecting it before it's covered.

On a real project

A structural concrete pour has an ITP specifying that rebar placement must be inspected and signed off before any concrete is placed, and that cylinder samples must be taken and tested at specific ages afterward. The crew knows not to pour until the rebar inspection sign-off is in hand, since the ITP makes that sequence a hard requirement rather than a suggestion.

Who this matters most to

The QA/QC Inspector performs the inspections and tests the ITP specifies and documents each sign-off, and the Quality Control Manager develops the ITP itself for each major scope item before work begins.

Where this goes wrong

A crew proceeds with the next step of work without confirming the ITP's required inspection sign-off actually happened first, and the project discovers the gap only after work that should have been inspected is already covered up and far more difficult to verify.