Lien Priority
The order in which competing claims against a property, such as a construction lien, a mortgage, and a tax lien, get paid out of the proceeds if the property is sold or foreclosed on, when there isn't enough money to pay everyone in full.
Why it matters
Construction liens don't automatically jump ahead of an existing mortgage; depending on the state, priority can run from the date the lien is recorded, the date work actually started on site, or another rule entirely, which is why the timing of a lien filing matters as much as the filing itself.
On a real project
A property goes into foreclosure with both a bank mortgage and a contractor's mechanic's lien outstanding. Because the state's priority rule ties lien priority to the date construction visibly began on site, and that date predates the mortgage recording, the contractor's lien is found to have priority over the bank's mortgage for the proceeds of the sale.
Who this matters most to
The Construction Attorney researches a state's specific lien priority rules before advising a client on how aggressively to pursue a lien claim, and the Construction Claims Consultant factors likely recovery given priority position into a claim's overall strategy.
Where this goes wrong
A contractor assumes filing a mechanic's lien guarantees getting paid ahead of the bank, without realizing that in many states a lien's priority date, not its filing date, determines where it actually ranks against an existing mortgage.