Schedule Performance Index (SPI)
A ratio comparing the value of work actually completed to the value of work that was planned to be completed by this point, used to measure whether a project is running ahead of or behind its planned schedule, independent of whether it's also running over or under budget.
Why it matters
CPI measures cost efficiency; SPI measures schedule efficiency, and a project can score well on one while scoring poorly on the other, so tracking SPI alongside CPI catches a schedule slip that a purely cost-focused report would miss entirely.
On a real project
A project has completed sixty percent of its planned work by a milestone date when the schedule called for seventy-five percent to be done by then. The resulting SPI below one flags a real schedule problem, even though the project's CPI that same month looks perfectly healthy, since the work that was completed happened to be done efficiently.
Who this matters most to
The Cost Engineer calculates SPI alongside CPI as part of routine project reporting, and the Scheduler investigates the underlying schedule slippage an SPI below one is actually pointing to.
Where this goes wrong
A project team tracks CPI closely but never calculates SPI, assuming a healthy cost position means the schedule must be fine too, and only discovers the project is genuinely behind once the finish date itself starts visibly slipping.