Scope Gap / Scope Overlap

A coordination problem where the written scope of work for two different subcontractors either leaves a piece of work assigned to neither of them, a gap, or assigns the same piece of work to both of them, an overlap, usually only discovered once work is actually ready to begin in the field.

Why it matters

A scope gap means nobody shows up to do a piece of necessary work until someone notices it's missing, often at the worst possible moment in the schedule, while a scope overlap wastes money paying for the same work twice or triggers a dispute between two subs over who's actually responsible for doing it.

On a real project

A general contractor discovers, right as rough-in is about to start, that neither the electrical nor the low-voltage subcontractor's scope of work actually includes running conduit for a specific security system, a scope gap that has to be resolved with a change order to one of the subs before work can proceed on schedule.

Who this matters most to

The Contracts Administrator reviews every subcontract's scope of work against the others before award specifically looking for gaps and overlaps, and the Project Manager resolves a gap discovered in the field quickly enough to avoid it becoming a schedule delay.

Where this goes wrong

Subcontracts are written and awarded without cross-checking each scope of work against the others, and a gap between two subs' scopes isn't discovered until a crew is standing on site ready to work and nobody is actually contracted to do the piece in front of them.