Spill Prevention, Control, and Countermeasure (SPCC) Plan
A written EPA-required plan, triggered once a facility's aggregate aboveground oil storage exceeds 1,320 gallons, detailing how the site prevents oil discharges into navigable waters, including secondary containment, inspection schedules, and spill response procedures, separate from the stormwater-focused SWPPP.
Why it matters
A jobsite running fuel tanks for generators and equipment can cross the 1,320-gallon threshold without anyone really noticing, since the trigger counts aggregate storage capacity across every container on site, not just one big obvious tank.
On a real project
A jobsite running several portable fuel tanks for generators and heavy equipment totals over 1,320 gallons of aggregate aboveground storage capacity, triggering the requirement for a written SPCC Plan even though no single tank on site looks large enough to draw attention on its own.
Who this matters most to
Project managers running fuel-heavy jobsites should total up every container's capacity across the whole site, not just the obviously large ones, since the SPCC threshold is based on the aggregate, not any single tank.
Where this goes wrong
Contractors sometimes confuse this plan with a project's stormwater pollution prevention plan, when the SPCC Plan specifically addresses oil discharge prevention under a separate EPA regulation, with its own distinct trigger threshold and its own separate written plan.