Suspension of Work Clause

A contract provision giving the owner the right to temporarily halt all or part of the construction work for a stated period, for the owner's own convenience or for cause, while generally entitling the contractor to an adjustment of time and sometimes cost for the resulting delay and remobilization expense.

Why it matters

Unlike termination, which ends the contract entirely, a suspension is meant to be temporary, and a well-drafted clause spells out how long a suspension can last before the contractor gains the right to treat it as a termination for convenience instead, which protects the contractor from being left indefinitely in limbo.

On a real project

An owner suspends work on a public project for several weeks while resolving a funding issue. The contractor demobilizes its crew and equipment during the suspension, then invokes the suspension clause to recover both the schedule extension and the documented cost of demobilizing and remobilizing once work resumes.

Who this matters most to

The Project Manager documents demobilization and remobilization costs during a suspension to support a later claim, and the Contracts Administrator tracks the suspension's duration against the contract's conversion-to-termination threshold.

Where this goes wrong

A contractor absorbs the cost of an owner-directed suspension without formally invoking the suspension clause or documenting its added cost, assuming it will simply be compensated later, and loses leverage to recover those costs once work resumes and the issue is no longer fresh.