Value Engineering Change Proposal (VECP)
A formal mechanism, common on public and federal contracts, letting a contractor propose a specific change to the contract's own requirements that would reduce cost without sacrificing required performance, with any resulting savings shared between the contractor and the owner under a pre-agreed formula.
Why it matters
Unlike general value engineering done during design, a VECP is submitted after the contract is already signed and specifically proposes changing what the contract itself requires, which is why it needs owner approval through a formal process rather than just being implemented as a normal construction decision.
On a real project
A contractor on a federal building project identifies a specified structural system that could be substituted for a less expensive alternative without reducing performance. The contractor submits a formal VECP documenting the proposed substitution and projected savings, and once the owner approves it, the contract is formally modified and the savings are split between the contractor and the owner under the contract's VECP sharing formula.
Who this matters most to
The Value Engineering Consultant helps develop and document a VECP's technical justification, and the Contracts Administrator processes the formal contract modification once the VECP is approved.
Where this goes wrong
A contractor implements a cost-saving substitution without going through the formal VECP approval process, assuming it's simply a normal construction decision, and loses the right to share in savings the mechanism would otherwise have entitled it to, since the change was never actually processed as a VECP.