Variance at Completion (VAC)
The difference between a project's original total budget and its currently forecasted final cost, calculated as budget minus Estimate at Completion, showing in dollar terms whether the project is now expected to finish under or over its original budget.
Why it matters
Unlike a simple month-to-date budget comparison, VAC looks all the way to the project's forecasted finish, so it can flag a cost problem that hasn't shown up in spending yet but is already baked into the current trend, giving the team time to react before the problem is actually realized in cash spent.
On a real project
A project's original budget is ten million dollars, but its current CPI trend puts its Estimate at Completion at eleven million. The resulting negative one-million-dollar VAC tells leadership the project is on pace to run over budget by that amount if nothing changes, well before that overrun actually shows up in a monthly spending report.
Who this matters most to
The Cost Engineer calculates VAC as part of routine cost reporting, and the Operations Manager uses a negative VAC trend across multiple projects to decide where leadership attention is most urgently needed.
Where this goes wrong
A project team watches monthly spending stay within budget and assumes everything is fine, without calculating VAC against the current cost performance trend, missing a forecasted overrun that spending reports alone won't reveal until it's already too late to correct.