Window Analysis (Schedule Delay)
A delay analysis technique that breaks a project's full duration into a series of shorter time periods, or windows, and examines how the critical path and schedule actually changed within each window, rather than comparing only the original baseline schedule to the final as-built result.
Why it matters
Looking only at the start and end dates can hide which specific events, happening in which specific windows, actually caused delay, since several different issues may have each eaten up float at different points in the project; a window analysis attributes delay to the period and cause where it actually occurred.
On a real project
A delay dispute covers an eighteen-month project with several different issues: a permit delay early on, a design change mid-project, and a weather event near the end. A window analysis breaks the project into several shorter periods and shows how the critical path shifted in each one, attributing specific delay days to each separate cause rather than lumping them all together.
Who this matters most to
The Scheduling Delay Consultant performs the window analysis to attribute delay to its actual cause and time period, and the Construction Claims Consultant uses that attribution to support or defend a delay claim.
Where this goes wrong
A party tries to prove delay by simply comparing the original baseline schedule to the final as-built finish date, without a window analysis breaking down which specific period and cause the delay actually came from, leaving the claim vulnerable to a challenge over whether a different party or event was really responsible.