Hold Point / Witness Point
Two levels of required inspection stops built into an inspection and test plan: a hold point is a mandatory stop where work legally cannot continue until a specific party signs off, while a witness point simply requires that party be notified and given the opportunity to observe, without actually stopping the work if they don't show up.
Why it matters
The distinction matters because a missed witness point is a documentation gap, while proceeding past a missed hold point without the required sign-off is a real compliance violation, which means the ITP has to clearly label which specific inspections are hold points and which are only witness points.
On a real project
An ITP designates rebar inspection before a structural pour as a hold point, meaning the crew legally cannot pour until the inspector signs off, but designates the inspector's observation of formwork stripping as only a witness point, meaning the crew can proceed on schedule even if the inspector isn't available to watch that specific step.
Who this matters most to
The QA/QC Inspector confirms which designated hold points actually require a sign-off before work proceeds, and the Superintendent schedules crews around hold points to avoid a costly standstill waiting on inspection availability.
Where this goes wrong
A crew treats a designated hold point like an ordinary witness point and proceeds with work when the required inspector doesn't show up on schedule, not realizing the work now has to be exposed again later for the sign-off that should have happened before it continued.