Percentage-of-Completion Accounting

The standard revenue-recognition method for long-duration construction contracts, recognizing revenue and profit gradually as a job progresses, based on costs incurred so far against total estimated costs, rather than waiting until the project finishes to recognize anything at all.

Why it matters

A multi-year project would otherwise show zero revenue for years and then one enormous number the month it finishes, a distorted picture that tells a bank, surety, or owner almost nothing useful about how the company is actually doing in any given year. Recognizing revenue as the work actually happens matches the financials to reality.

On a real project

A $2,000,000 contract has incurred $600,000 of its total estimated $1,200,000 in costs, putting it at 50 percent complete. Percentage-of-completion accounting recognizes $1,000,000 of revenue for that period, half of the total contract, not zero and not the full amount.

Who this matters most to

A Construction Accountant applies percentage-of-completion revenue recognition across every active project each reporting period. A Controller/CFO relies on it to produce the company-wide financial statements a surety reviews each year to set the company's bonding capacity, since a sloppy or inconsistent application of this method directly undermines a surety's confidence in the numbers.

Where this goes wrong

A company underestimates a project's total remaining costs partway through the job, which makes the project look further along, and therefore more profitable, than it actually is. Revenue gets over-recognized for several quarters before the real cost overrun surfaces, and the correction then hits all at once as a sudden, hard-to-explain loss in a single reporting period.