Work-in-Progress (WIP) Report
A monthly schedule, one line per active job, comparing how much of a contract has actually been earned based on progress against how much has actually been billed, surfacing every project as either over-billed (billed ahead of progress) or under-billed (billed behind progress).
Why it matters
A contractor can look profitable on a single invoice and still be quietly losing money, or look behind on billing and still be in fine shape, depending on how its billing compares to its real progress. The WIP report is the one document that catches this directly, which is exactly why a surety or bank reviewing a contractor's financial health asks for it by name.
On a real project
A $1,000,000 contract is 60 percent complete, meaning $600,000 of revenue has been earned, but the contractor has only billed $500,000 so far. The WIP report flags this job as under-billed by $100,000, a real asset the contractor hasn't collected yet, not a problem, but something worth billing for soon.
Who this matters most to
A Construction Accountant prepares the WIP report every month across all active jobs, and a Controller/CFO reviews it company-wide for anomalies, since a job that's badly over-billed can mean the company is about to run out of cash on it once the remaining work doesn't generate enough new billing to cover costs.
Where this goes wrong
A project manager keeps billing ahead of actual progress to improve cash flow, assuming the work will eventually catch up. It doesn't, and by the time the WIP report flags how far over-billed the job has become, there's no remaining contract value left to bill against the work still unfinished, turning what looked like healthy cash flow into a real loss on paper.