Skip to main content
Concept

Selective Demolition

CSI Division 02, Existing Conditions

The targeted removal of specific building elements -- a single wall, a section of roofing, interior finishes -- while leaving the surrounding structure intact, as opposed to full demolition that clears an entire building or structure.

Why it matters

Selective demolition lets a renovation or addition proceed without destroying parts of the building the owner wants to keep, but it requires more care than full demolition since the crew has to protect what's staying while removing what isn't.

On a real project

A contractor renovating a single floor of an occupied office building selectively demolishes interior partition walls and ceiling tile on that floor only, using dust barriers and negative-air equipment to keep the work from disrupting tenants on other floors.

Who this matters most to

A Demolition Supervisor sequences selective demolition to avoid compromising structural elements, and a Structural Engineer signs off when removal touches anything load-bearing.

Where this goes wrong

A crew removes a wall during selective demolition without confirming it isn't load-bearing, and the floor above sags before the error is caught, turning a planned interior renovation into an unplanned structural repair.