Utility Locate (811 / One-Call)

The legally required process of contacting the national 811 call-before-you-dig system before any excavation, triggering utility owners to mark the approximate location of their buried lines with color-coded paint or flags within a required notice period that varies by state, typically a few business days.

Why it matters

This is the notification and marking step itself, required by law before excavation begins; it's a separate step from potholing, which physically confirms a marked line's exact depth once the general area has already been located and marked.

On a real project

A contractor planning to trench for a new utility line submits an 811 request several business days before the scheduled work, as required by state law. Utility owners respond by marking the approximate location of their buried lines with color-coded paint, red for electric, yellow for gas, blue for water, giving the crew a general picture of what's underground before any digging begins.

Who this matters most to

The Superintendent submits the 811 request far enough ahead of planned excavation to meet the state's required notice period, and the Permit Expediter sometimes tracks 811 requests alongside other pre-construction regulatory requirements.

Where this goes wrong

A crew begins excavation without submitting an 811 request first, or without waiting out the required notice period, and strikes a utility line that would have been marked and avoided if the legally required notification process had actually been followed.